Close-up of underground station S9 of Hanoi’s second metro line

Construction of the S9 station is expected to be completed in about five months, and construction of the whole station will be finished in late 2020.

Nhon - Hanoi Railway, Hanoi’s second metro line after the Cat Linh-Ha Dong, has four underground stations: S9, 10, 11 and 12. The main level of Station S9 is under construction to connect up to the streets or down to the platforms via elevators, Kinhtedothi.vn reported.

The S9 station’s main level is 19 meters below the ground. It is 23,3 meters wide, 186,6 meters long. Its construction is expected to be completed in about five months, and construction of the whole station will be finished in late 2020.

Shaun Atkins, chief engineer of Package CP-03, Hyundai E&C - Ghella Joint Venture, said that the project was interrupted for a few days due to the Covid-19 pandemic.

However, they are speeding up the pace and making effort to complete the project on time, Shaun Atkins added.

The Nhon-Hanoi Railway Station route is 12.5 kilometers long from Nhon area in the western district of Nam Tu Liem, going through Kim Ma street to the Hanoi Railway Station in the downtown. It will run 8.5 kilometers on elevated tracks through eight stations and the remaining four kilometers underground. The underground track is scheduled to begin operation in 2022.

The total cost of the project has been revised up to EUR1.176 billion. Of the total, EUR178.7 million is funded with ODA provided by the French Development Agency (AFD) and EUR355.1 million is lent by the French government.

It is one of several metro lines planned for the capital city to ease traffic congestion and reduce emissions.

The followings are photos taken at Underground station S9:

Construction progress of Station S9 is being sped up.

 Two pipes of the ventilation system.

 Preparing to pour concrete to the floor.

 Checking and waterproofing the diaphragm wall of the S9 terminal.

 Technical supervision in the main level.

 Machines work in three shifts a day.

 An elevator for transporting workers.

 A crane transporting materials to the underground works.

Reactions:
Share:
Trending
Most Viewed
Related news
Hanoi health sector targets digital leap under new Party resolution

Hanoi health sector targets digital leap under new Party resolution

Hanoi sets 2026 as a breakthrough year for healthcare reform, accelerating digital transformation, restructuring hospital networks and tightening food safety management under Politburo Resolution 72.

Hanoi launches state-backed innovation hub to drive digital economy

Hanoi launches state-backed innovation hub to drive digital economy

The new innovation center is designed to connect policy, technology and talent, aiming to accelerate digital transformation, support startups and position the capital as a global testing hub for emerging technologies and creative industries.

Hanoi issues action plan to implement 14th Party Congress resolution

Hanoi issues action plan to implement 14th Party Congress resolution

The goal is to turn policies into outcomes under the principle of “less talk, more action, effective results to the end, all for the capital and its people.”

ASEAN youth chart next phase of climate action in Hanoi

ASEAN youth chart next phase of climate action in Hanoi

Home to more than 680 million people, many in vulnerable coastal and low-lying areas, ASEAN is on the front line of climate change, facing rising seas, fiercer storms, prolonged droughts and accelerating biodiversity loss that endanger the region’s economic resilience and social stability.

Hanoi launches sweeping overhaul to unlock state economy growth

Hanoi launches sweeping overhaul to unlock state economy growth

Hanoi has unveiled an ambitious five-year plan to reform governance, mobilize public assets and restructure state enterprises, aiming to turn the state economy into a powerful engine of sustainable growth.

Hanoi puts people first in implementing four strategic Party resolutions

Hanoi puts people first in implementing four strategic Party resolutions

Hanoi launches comprehensive action plans to implement Politburo Resolutions 71, 72, 79 and 80, prioritizing people-centered reforms in education, healthcare, culture and state economic development.

Vietnamese families blend Tet travel trends with enduring traditions

Vietnamese families blend Tet travel trends with enduring traditions

More young Vietnamese families choose travel over staying home during the Lunar New Year holiday, seeking fresh experiences while keeping core traditions intact.

Hanoi Party Chief backs Hoa Lac Hi-tech Park as strategic tech hub

Hanoi Party Chief backs Hoa Lac Hi-tech Park as strategic tech hub

The vision is for Hoa Lac to become a growth pole for Hanoi, driving innovation and high-tech development while advancing sustainable growth across the wider Capital Region.