At the end of July, the section of the Nhon-Hanoi Railway Station is completed almost in half.
The Nhon-Hanoi Railway Station metro line’s first ten trains will be brought from France to Hanoi in March 2020, according to Head of Hanoi Metropolitan Railway Management Board (MRB) Nguyen Cao Minh.
Minh said on July 31 that the French contractor is producing the first trains for the Nhon-Hanoi Railway Station metro line.
"We are urging the contractor to step up the work to meet the deadline of putting the elevated section of the line in operation by 2020," Minh added.
The ten aluminum-alloy trains will be built according to European standards. Each train will have four or five cars that are 2.75-3.0 meters wide and 80-100 meters long in total for each train. Handles for standees will be designed to match Vietnamese people’s height.
The train design was submitted by the French contractor to MRB, and then made public in 2018 for consultation. The survey results show that more than 80% of respondents agreed with the design.
The trains cost VND7.7 trillion ($331 million), of which almost VND3 trillion ($129 million) will be spent on consulting, designing and assembling, while the rest is intended to cover the cost of rail tracks and train depots.
At the end of July, the section of the Nhon-Hanoi Railway Station is completed almost in half. Its elevated sections are 99.5% completed and work on these is being prioritized to meet the deadline next year, while the underground section has been built only 5%, according to the MRB.
The Nhon-Hanoi Railway Station route, the capital’s second metro line after the Cat Linh-Ha Dong route, runs 12.5 kilometers from Nhon area in the western district of Nam Tu Liem, via Kim Ma street to Hanoi Railway Station in the downtown. It will run 8.5 kilometers on elevated tracks through eight stations and the remaining four kilometers underground. The underground track is scheduled to begin operations in 2023.
Hanoi’s first metro line, connecting Cat Linh Station in downtown Dong Da district to the Yen Nghia Station in Ha Dong district, which is said to be 99% completed, has missed its deadline several times. Hanoi’s authority said it would borrow US$1.48 billion from official development assistance (ODA) funds to build a new metro section in 2021.
Minh said on July 31 that the French contractor is producing the first trains for the Nhon-Hanoi Railway Station metro line.
Model of the urban railway train, route No.3, from Nhon to Hanoi Railway Station
|
The ten aluminum-alloy trains will be built according to European standards. Each train will have four or five cars that are 2.75-3.0 meters wide and 80-100 meters long in total for each train. Handles for standees will be designed to match Vietnamese people’s height.
The train design was submitted by the French contractor to MRB, and then made public in 2018 for consultation. The survey results show that more than 80% of respondents agreed with the design.
The trains cost VND7.7 trillion ($331 million), of which almost VND3 trillion ($129 million) will be spent on consulting, designing and assembling, while the rest is intended to cover the cost of rail tracks and train depots.
At the end of July, the section of the Nhon-Hanoi Railway Station is completed almost in half. Its elevated sections are 99.5% completed and work on these is being prioritized to meet the deadline next year, while the underground section has been built only 5%, according to the MRB.
The Nhon-Hanoi Railway Station route, the capital’s second metro line after the Cat Linh-Ha Dong route, runs 12.5 kilometers from Nhon area in the western district of Nam Tu Liem, via Kim Ma street to Hanoi Railway Station in the downtown. It will run 8.5 kilometers on elevated tracks through eight stations and the remaining four kilometers underground. The underground track is scheduled to begin operations in 2023.
Hanoi’s first metro line, connecting Cat Linh Station in downtown Dong Da district to the Yen Nghia Station in Ha Dong district, which is said to be 99% completed, has missed its deadline several times. Hanoi’s authority said it would borrow US$1.48 billion from official development assistance (ODA) funds to build a new metro section in 2021.
Other News
- Vietnam-Singapore Friendship Association launched in Hanoi to strengthen bilateral ties
- Hanoi, HCMC to submit metro plans to National Assembly in February: Deputy PM
- Hanoi integrates administrative procedures into national public service portal
- 2025 spring book fair opens to boost reading in Hanoi
- Traditional essence in Hanoi's Old Quarter Tet celebration program
- Annual Tet flower market opens in Hoan Kiem District
- Thousands of people rejoice Hanoi International Light Festival 2025
- HUFO looks back at 2024 with impressive results
- More than 2,000 drones paint Hanoi's landmarks in New Year's skies
- Hanoi accelerates completion of Ring Road No. 4 service roads in 2025
Trending
-
Vietnam, Switzerland upgrade bilateral ties to comprehensive partnership
-
Vietnam news in brief - January 22
-
Tet homework? Yes, but keep it light to avoid stress for students
-
Vietnam hosts first international lantern competition
-
Hanoi kicks off the Spring Calligraphy Festival in celebration of Lunar New Year
-
Hanoi’s central role means heightened responsibility in foreign affairs: Mayor
-
Hanoi revives historic Tet traditions in Duong Lam Ancient Village
-
AI set to drive Vietnam's economic growth in 2025
-
Two Vietnamese cities in Asia's top five destinations for digital nomads