Power shortage threatens South of Vietnam due to the delay of power projects.
Power shortage may cast its shadow over Vietnam in 2020 and afterwards, mostly in the southern region due to the sluggishness of many energy projects, local media reported, citing the Ministry of Industry and Trade.
The country may face the power shortage in 2020 if diesel-fired generators fails to meet the required capacity or lack of fuel (coal and gas) for the power generation, according to the ministry.
It said that the diesel-fueled power mobilized for 2019 would be 1.7 billion kWh and might reach 5.2 billion kWh by 2020.
More seriously, the power shortage might happen in the southern region in 2021-2025 due to rising consumption volume. The shortage might hit 3.7 billion kWh in 2021, nearly 10 billion kWh in 2022, 12 billion kWh in 2023, 7 billion kWh in 2024, and 3.5 kWh in 2025.
Under the revised Power Plan VII, the country’s total capacity may reach 95,700 MW for the 2016-2030 period but the realistic figure would be around 80,200 MW.
The power shortage in the south would be largely created by the delay of gas projects namely Block B and Ca Voi Xanh (Blue Whale) – Vietnam’s largest offshore gas project off the central city of Danang discovered in 2011 with reserves of 150 billion cu.m.
In addition, Kien Giang 1 and 2 Thermal Power projects and O Mon 2 Gas-fired Power project would fail to come operational in 2021-2025.
In case Long Phu 1 Thermal Power project fails to meet the completion deadline by 2023, the situation would be worse in 2024-2025, the ministry predicted.
The annual growth of power consumption in Vietnam in the 2016-2020 is around 10.34%-11.26%.
Illustrative photo
|
The country may face the power shortage in 2020 if diesel-fired generators fails to meet the required capacity or lack of fuel (coal and gas) for the power generation, according to the ministry.
It said that the diesel-fueled power mobilized for 2019 would be 1.7 billion kWh and might reach 5.2 billion kWh by 2020.
More seriously, the power shortage might happen in the southern region in 2021-2025 due to rising consumption volume. The shortage might hit 3.7 billion kWh in 2021, nearly 10 billion kWh in 2022, 12 billion kWh in 2023, 7 billion kWh in 2024, and 3.5 kWh in 2025.
Under the revised Power Plan VII, the country’s total capacity may reach 95,700 MW for the 2016-2030 period but the realistic figure would be around 80,200 MW.
The power shortage in the south would be largely created by the delay of gas projects namely Block B and Ca Voi Xanh (Blue Whale) – Vietnam’s largest offshore gas project off the central city of Danang discovered in 2011 with reserves of 150 billion cu.m.
In addition, Kien Giang 1 and 2 Thermal Power projects and O Mon 2 Gas-fired Power project would fail to come operational in 2021-2025.
In case Long Phu 1 Thermal Power project fails to meet the completion deadline by 2023, the situation would be worse in 2024-2025, the ministry predicted.
The annual growth of power consumption in Vietnam in the 2016-2020 is around 10.34%-11.26%.
Other News
- Year-end hiring spree as Hanoi companies ramp up recruiting
- Vietnam's digital economy expected to grow big in 2024
- Incheon-Hanoi conference marks milestone in tourism development cooperation
- Hanoi's businesses place focus on digital transformation
- Semiconductor market reaches $18.2 billion: SEMIEXPO Vietnam 2024
- Hanoi DigiTech 2024 connects businesses through digital products
- Hanoi steps up investment promotion
- Hiring multitaskers: Priority for Hanoi companies
- Hanoi seeks partnerships to build skilled workforce for digital transformation
- Hanoi to host Vietnam-Asia Smart City Summit 2024
Trending
-
Indochina Sense: Hanoi’s architectural heritage unveiled at a 100-year-old university
-
Vietnam news in brief - November 17
-
Hanoi records strong tourism growth in first ten months
-
“Look! It’s Amadeus Vu Tan Dan” workshop - an artistic journey for kids
-
Vietnam news in brief - November 15
-
Experiencing ingenious spaces at the Hanoi Creative Design Festival 2024
-
Hanoi Festival of Creative Design 2024: celebrating the capital's cultural innovation
-
Expatriate workforce in Hanoi: Growth engine requring thorough administration
-
Ethnic minorities want more policies for socio-economic improvement
-
Liên kết hữu ích
- Make up hàn quốc tone hồng nổi bật