The Prime Minister has approved a special mechanism to complete Hanoi’s Cat Linh-Ha Dong urban railway project in an effort to address numerous delays and cost overruns.
The Cat Linh-Ha Dong urban railway project was supposed to be completed by the end of this year. However, only 74% of the project has been finished since it broke ground in September 2010, according to the project’s management unit.
The investment in the project increased from a projected 542 million USD in 2008 to 892 million USD in 2014.
According to the special mechanism, proposed by the Ministry of Transport, the main contractor (China Railway Sixth Group) will be authorised to make decisions, especially on buying equipment, without having to seek time-consuming permission from State authorities. However, the contractor must ensure that prices do not exceed those set out in the signed contract.
The investment in the project increased from a projected 542 million USD in 2008 to 892 million USD in 2014.
According to the special mechanism, proposed by the Ministry of Transport, the main contractor (China Railway Sixth Group) will be authorised to make decisions, especially on buying equipment, without having to seek time-consuming permission from State authorities. However, the contractor must ensure that prices do not exceed those set out in the signed contract.
Regarding the selection of foreign contractors for safety assessments, the Prime Minister has agreed in principle that contractors will be chosen in accordance with Article 26 of the Law on Bidding, ensuring that selected contractors are qualified, have adequate experience and meet the requirements of the tender package.
On additional loans for the project, the Ministry of Planning and Investment and the Ministry of Finance were urged to promptly work with the Chinese side on reaching agreement on supplement preferential loans for the project.
The Prime Minister required the Ministry of Transport to review the preparation and implementation of the project as a lesson for the next steps of the project and other projects to ensure the efficiency, quality assurance and construction progress.
Other News
- Hanoi's top priority is to keep students safe while traveling
- Hanoi pioneers in using interoperable smart cards for public transport
- Hanoi to establish customer service hub for administrative reform
- Hanoi tops country for blood donation in 2024
- Hanoi disseminates safe eating practices
- Hanoi upholds great national unity bloc
- Hanoi to auction 36,000 trees damaged by Super Typhoon Yagi
- Elite firefighting and rescue teams set up in Hanoi
- Hanoi steps up efforts to combat smuggling and trade fraud
- Hanoi administers more vaccine doses to residents
Trending
-
Hanoi eyes greater global integration in years to come
-
Vietnam news in brief - December 15
-
Exhibition of 20th century Vietnamese art: A rendezvous with masters of painting
-
Hanoi approves Soc Son District Zoning plan
-
Hanoi's artisan carries on lantern making art
-
EVs take the spotlight on Vietnam's urban streets
-
Thay Pagoda: A timeless heritage on Hanoi's outskirts
-
Hanoi's pho declared national intangible heritage
-
Christmas in Vietnam: A blend of Western cheer and local charm