Sep 14, 2019 / 12:05
Disbursement rate of ODA funds in Vietnam reaches 3.4% of targets in Jan-Jun
Minister of Finance Dinh Tien Dung attributed the low disbursement rate to delay in assigning mid-term public investment plan, insufficient fund allocation, slow adjustment of investment plan, cumbersome procedures, or delay in completing disbursement procedures.

![]() Overview of the conference. Source: Tuoitre Newspaper.
|
In the 2016 – 2018 period, total investment capital from the ODA and preferential loans stood at VND137.17 trillion (US$5.95 billion), or 74.53% of the estimate.
Regular spending from foreign sources in the January – August period reached VND862 billion (US$37.41 million), or 8.5% of the estimate.
As of present, 35 government agencies and provinces recorded low disbursement rate, such as the Ministry of Health with 4.8%, Quang Ninh province with 0.5%, Quang Nam with 2.3%, Hung Yen with 8.3%, among others.
Dung attributed the low disbursement rate to delay in assigning mid-term public investment plan, insufficient fund allocation, slow adjustment of investment plan, cumbersome procedures, or delay in completing disbursement procedures.
Dung referred to the case of Ministry of Education and Training (MoET) having disbursement rate of 25% of the estimate, citing the lack of counterpart funds as the reason.
Additionally, representative of the MoET said the process of fund allocation is time consuming, in which the planning often takes one to three months, and only until the third quarter then the ODA funds starts getting disbursed.
To speed up the disbursement rate of ODA and preferential loans, Ngo Van Quy, vice chairman of Hanoi People’s Committee proposed the mechanism of disbursing ODA funds based on actual implementation progress and the fund provision plan of donors.
Quy pointed to the pilot urban railway project of Hanoi with section Nhon – Railway Station which invested with an estimated fund of VND3.27 trillion (US$141.69 million). However, as of the end of August, only VND1.1 trillion (US$47.65 million) has been allocated, or 34% of the estimate.
Another example is the Hanoi urban railway project section South Thang Long – Tran Hung Dao with the disbursement rate of 5% of the estimate. IN 2019, the allocation plan was VND393 billion (US$17 million), but only VND18.4 billion (US$796,904) has been disbursed to date.
Other News
- Local banks cut interest rates in response to PM’s request
- Vietnam set to have digital banks within financial centers
- Hanoi expands cashless parking pilot program
- Prime Minister urges banks to prioritize economic support over profits
- Vietnamese Gov’t forecasts CPI growth of up to 4.5% in 2025
- Vietnam prioritizes agriculture and renewable energy for access to green loans
- Vietnam GDP expands by 7.09% in 2024
- Vietnam stock market set to accelerate in 2025: Experts
- Vietnam stock market aims for emerging status by 2025: Finance minister
- Vietnam set to extend VAT cut for six months
Trending
-
New Zealand’s Prime Minister visits Vietnam’s first university
-
Vietnam news in brief - February 27
-
Vietnam’s diplomacy through Comprehensive Strategic Partnership
-
Most pleasurable ways to explore Hanoi
-
Vivid yellow flowers brighten spring in Hanoi
-
Vietnam heritage painting contest launched
-
Vietnam scales back plan to boost offshore wind
-
Indochina fine arts heritage in the heart of Hanoi
-
Keeping the spirit of Vietnamese folk paintings alive