Hanoi will shorten the time needed to process applications and grant construction permits from 166 days at present to no longer than 120 days in line with a prime minister instructive dated March 13, 2018.
The municipal People’s Committee has assigned the Department of Construction to review construction-related procedures and make proposals on ways to achieve the target and report to the municipal People’s Committee before June 20.
The People’s Committee also instructed local administrations, agencies and sectors to quickly review the process of related procedures under their management such as granting land use certificate (commonly know as red book in the country), supplying electricity and water and assessing fire prevention of buildings with a view to reducing the processing time.
Accordingly, the city’s electricity and water supply companies should work to reduce the time for electricity and water connection from 14 days to not more than 7 days.
The Hanoi Fire Fighting and Prevention Police Deparment is required to cut the time for evaluating fire prevention schemes of construction works from 30 days to 20 days at most.
The People’s Committees at lower levels are instructed to review construction-related procedures within their power with a view to shortening the time taken to complete them.
The municipal Department of Natural Resources and Environment is required to work to shorten the time for granting land use certificates and land-related property ownership certificates from 30 days to 20 days at most.
All relevant departments, agencies and sectors must report the pace of their work to the Department of Construction before June 15, 2018.
A construction site in Hanoi
|
Accordingly, the city’s electricity and water supply companies should work to reduce the time for electricity and water connection from 14 days to not more than 7 days.
The Hanoi Fire Fighting and Prevention Police Deparment is required to cut the time for evaluating fire prevention schemes of construction works from 30 days to 20 days at most.
The People’s Committees at lower levels are instructed to review construction-related procedures within their power with a view to shortening the time taken to complete them.
The municipal Department of Natural Resources and Environment is required to work to shorten the time for granting land use certificates and land-related property ownership certificates from 30 days to 20 days at most.
All relevant departments, agencies and sectors must report the pace of their work to the Department of Construction before June 15, 2018.
Other News
- Hanoi to rent nearly 900 sidewalks next year
- Quoc Oai District breaks ground on industrial clusters
- Stronger decentralization key to Hanoi's urban railway ambitions
- Prime Minister urges acceleration of social housing projects
- Hanoi Forum explores innovative solutions for sustainable urban development
- Prime Minister urges Chinese companies to collaborate on infrastructure projects
- Lao Cai – Hanoi – Haiphong railway section to be built in 2027
- New supply to boost Hanoi retail property market
- Vietnam, China cross-border railway project to start construction in 2025
- Hanoi approves 14 residential projects amid market challenges
Trending
-
Homeland Spring 2025: Overseas Vietnamese explore investment opportunities
-
Vietnam news in brief - January 17
-
More than 2,000 drones paint Hanoi's landmarks in New Year's skies
-
Hanoi kicks off the Spring Calligraphy Festival in celebration of Lunar New Year
-
Hanoi’s central role means heightened responsibility in foreign affairs: Mayor
-
Hanoi revives historic Tet traditions in Duong Lam Ancient Village
-
AI set to drive Vietnam's economic growth in 2025
-
Two Vietnamese cities in Asia's top five destinations for digital nomads
-
Prime Minister sets vision for Vietnamese football: Asian glory and World Cup dreams
-
Liên kết hữu ích