TOD model for solving urban traffic challenges in Hanoi

Under the current implementation method and situation, the completion of nearly 600 km of urban rail lines in Hanoi and Ho Chi Minh City in the next 12 years is not feasible. Therefore, a change is essential.

Nguyen Phi Thuong, Director of the Hanoi Department of Transport, told Hanoimoi Newspaper that the TOD (Transit-Oriented Development) model is a way to address the existing challenges of urban transport.

 The Cat Linh - Ha Dong metro line. Photos: Pham Hung/ The Hanoi Times

What are the reasons behind the challenges faced by the metro projects in Hanoi and Ho Chi Minh City in meeting the 12-year deadline?

According to the plan, Hanoi aims to construct 10 metro lines totaling 417 kilometers, with an estimated total investment of about $40 billion. Similarly, Ho Chi Minh City is considering the development of eight lines totaling 220 kilometers, requiring an approximate investment of $25 billion.

Nonetheless, the execution of the proposed lines is currently progressing at a sluggish pace. Up to now, Hanoi has only managed to open the Cat Linh-Ha Dong railway line. The 8.5-kilometer elevated segment of the Nhon - Hanoi Station metro line is anticipated to commence operations by the conclusion of the third quarter of 2023. In Ho Chi Minh City, solely the Ben Thanh - Suoi Tien metro line No. 1 is undergoing trial operation.

The investment demands for urban railway projects are substantial, surpassing the capabilities of the State budget. Recent urban railway ventures have unveiled numerous inadequacies. Alongside gradual advancement, there have been instances of cost overruns that have inflated the overall investment amount.

The urban metro lines lack harmonization with urban space restructuring and integration with the existing transportation system. Moreover, challenges in station accessibility undermine the efficiency of mass transit. Additionally, each railway line employs distinct technologies based on the sponsors' circumstances.

The achievement of a complete urban railway network in Hanoi and Ho Chi Minh City is projected by 2035, in accordance with the Development Orientation of Vietnam's Railway Transportation to 2030, with a perspective extending to 2045, sanctioned by the Politburo.

However, given the present implementation approach and circumstances, accomplishing the remaining nearly 600 kilometers of urban railway within the next 12 years poses considerable challenges.

What feasible solutions could be implemented to accomplish the objective?

 Nguyen Phi Thuong, Director of the Hanoi Department of Transport

Presently, the Transit-Oriented Development (TOD) model is being explored and implemented by numerous countries and cities worldwide as a long-term solution to address significant urban development issues, including infrastructure congestion, traffic congestion, environmental pollution, shortages in social housing, and inadequate investment resources for infrastructure expansion.

TOD is an urban development approach centered around public transport hubs, typically railway stations, that integrate diverse functions such as residential, office, financial, and commercial activities in the vicinity of the station area, spanning a maximum radius of 800-1,000 meters. This range corresponds to commuters' 10-15 minute walk to the station.

At the heart of TOD lies the synergy between public transportation and land utilization, encouraging vertical urban growth (compact cities) instead of sprawling horizontally.

Through the emphasis on public transportation, the model ensures sustainable urban advancement while generating resources for the maintenance and augmentation of public transport services.

The model is primarily reliant on rail transport, although it can also be implemented in conjunction with bus rapid transit systems.

Is it feasible for Hanoi and Ho Chi Minh City to adopt the TOD model?

Drawing from international examples, it is imperative for both Hanoi and Ho Chi Minh City to explore and implement the TOD model to facilitate the growth of their urban rail systems and uphold the overarching, sustainable urban development vision.

This entails synergizing governmental leadership with the resources and inventive capabilities of the private sector, transforming it into a propelling force for progress.

Revamping the present investment strategies for urban rail networks is critical, and the TOD model presents a viable solution to the multifaceted urban transportation issues confronting both cities. 


So what needs to be done to successfully implement the TOD model?

The elevated section of the Nhon - Hanoi Station metro line. 

Implementing TOD is a complex and lengthy process that requires extensive research and the involvement of multiple stakeholders at multiple levels.


As a result, the model always presents risks and challenges that must be thoroughly examined. Successful TOD models in practice have shown the need for four fundamental elements, including political vision and determination, mechanisms and policies for integrating transportation and land use in urban development, coordination mechanisms among stakeholders involved in TOD development, and financial mobilization mechanisms and risk-sharing arrangements.

Adapting to specific circumstances, cities can execute Transit-Oriented Development (TOD) initiatives through various mechanisms.

The fundamental principle behind TOD implementation involves amalgamating rail, bus rapid transit, and real estate development undertakings into a unified system. This can be achieved through avenues like public-private partnerships (PPP), leveraging property taxes and transfer fees, or leasing/auctioning land use rights to investors to procure funds for transportation expansion.

What are your suggestions for accelerating the implementation of TOD in Vietnam, given that this model is still new and lacks a legal framework?

I believe the initial step involves revisiting and enhancing the legal framework associated with the TOD model across domains such as land, planning, investment, construction, real estate business, public-private partnerships (PPP), and other relevant regulations, with the aim of ensuring harmonization.

The government should task pertinent ministries and agencies with formulating an appropriate TOD development strategy that factors in Vietnam's specific circumstances.

It should also permit the initiation of pilot projects based on this model in select cities, initially concentrating on the urban rail lines in Hanoi and Ho Chi Minh City. This iterative process can lead to the refinement of an effective and enduring TOD development strategy.

Individual municipalities should engage in research and release resolutions and strategies tailored explicitly for TOD, recognizing it as a central and prioritized solution for sustainable urban advancement.

They should review and adapt urban rail network blueprints to incorporate TOD models at stations and depots, considering the feasibility of land reclamation and urban growth.

Furthermore, it is essential to establish specialized mechanisms and policies to incentivize investor participation in TOD ventures rooted in the principles of equitable benefit distribution and shared risks.

Thank you!

Reactions:
Share:
Trending
Most Viewed
Related news
Hanoi apartment market heads for major supply surge beginning in 2026

Hanoi apartment market heads for major supply surge beginning in 2026

Hanoi’s apartment market is entering a new growth phase with a strong supply wave expected from 2026 as major projects launch across all segments from social housing to high-end developments.

Two social housing projects offered for sale as Hanoi strives to meet mounting demand

Two social housing projects offered for sale as Hanoi strives to meet mounting demand

Hanoi launches sales for CT-05 and CT-06 social housing projects in Quang Minh Commune, offering low-cost units as the city faces rising housing pressure.

Vietnam creates National Housing Development Fund to boost social housing supply by 2030

Vietnam creates National Housing Development Fund to boost social housing supply by 2030

Vietnam has taken a major step toward expanding affordable housing by establishing the National Housing Development Fund, a new financial mechanism designed to accelerate social housing development and stabilize the property market.

Hanoi to see sharp jump in land prices under new 2026 pricing framework

Hanoi to see sharp jump in land prices under new 2026 pricing framework

The sharp increases raise concerns over affordability, investment risks and shifting market behavior as land values climb across diverse areas of the city.

Hanoi to launch $34 million canal project to curb flooding, revive To Lich River

Hanoi to launch $34 million canal project to curb flooding, revive To Lich River

Hanoi starts a $34-million project to upgrade Thuy Phuong Canal, improve drainage and restore To Lich River flow with completion expected by Q3/2026.

Hanoi greenlights sub-zone B of 16,000-hectare southern sports and housing project

Hanoi greenlights sub-zone B of 16,000-hectare southern sports and housing project

The sub-zone B is designed to be a complex containing sports facilities, housing, public services, schools and agricultural land, with an estimated accommodation of 250,000–285,000 residents.

Strong public participation to drive Hanoi’s sustainable and dynamic urban growth

Strong public participation to drive Hanoi’s sustainable and dynamic urban growth

Hanoi’s development depends on effective planning, mobilization of social resources and clear decentralization with accountability and transparency.

Hanoi housing prices surge sharply in Q3/2025 amid limited supply

Hanoi housing prices surge sharply in Q3/2025 amid limited supply

Hanoi apartment prices remained high in Q3/2025, rising sharply amid limited supply and growing affordability concerns.