Log in
Hanoi

Cat Linh - Ha Dong Railway delays commercial run again

According to an official of the Railway Project Management Board under the Ministry of Transport, the Cat Linh - Ha Dong Railway project still encounters numerous difficulties and obstacles and is not eligible for commercial run.

Hanoians were told that their first urban railway line was expected to begin running at the end of April after several delays, but once more, its commercial operation has been postponed, local media reported.

The US$886 million project was initially slated to begin operation in 2016 but multiple setbacks pushed the date for launching to the end of 2019’s first quarter.
 
Cat Linh - Ha Dong Railway delays commercial run once more. Photo: Ngoc Hai
Cat Linh - Ha Dong Railway delays commercial run once more. Photo: Ngoc Hai
Earlier, China Railway Sixth Group, which is the Engineering-Procurement and Construction (EPC) contractor of the project, conducted the test of Cat Linh - Ha Dong Railway from October 2018, saying they would put it into commercial run after three or six months, or before the Tet holiday, which fell in early February.

In February, the EPC General Contractor once more said that they expected to complete the trial run and the official launch would be conducted at the end of the first quarter of 2019.

In the mid-March check, Minister of Transport Nguyen Van The requested the EPC contractor and related units to complete the remaining workload to put the trains into operation in late April 2019. Until now, it cannot be confirmed when the Cat Linh - Ha Dong line will enter operation.

According to an official of the Railway Project Management Board under the Ministry of Transport, the project still encounters numerous difficulties and obstacles and is not eligible for commercial run. 

"The EPC contractor lacks experience in implementing projects, fails to assigned well-qualified personnel, and delays completion for documents of all kinds. Although the Railway Project Management Board pushes them drastically and removes obstacles, the general contractor has still been unable to complete the documents," the official was quoted by Kinh te Do thi newspaper as saying.

Besides, after finishing the test, the railway will be appraised by the Vietnam Register and an independent unit of France. Then, it will be handed over to Hanoi city for management, which means the operation of the railway will not be seen any time soon. 

The Cat Linh - Ha Dong line is one of the key public transport projects in Hanoi. Since September 2018, all 13 trains have been tested, with the average speed of 35 km/hour. The railway is 13.5km length and uses standard-gauge rail track (1,435mm). The designed speed of the track reaches 80km/h.

Hanoi Railway Company also said that it has submitted to the Hanoi People's Committee two options for Cat Linh - Ha Dong railway’s ticket pricing. Accordingly, monthly travel pass pricing is VND200,000 (US$8.6), 24-hour card is priced at VND30,000 (US$1.29) and VND8,000 (US$ 0.344) per person for a ride. Ticket prices will vary depending on the distance. 

According to the plan, in the first days, Cat Linh - Ha Dong line will provide free service for passengers, with an aim to lure people to public transport. 
Reactions:
Share:
Trending
Most Viewed
Hanoi to build Tran Hung Dao Bridge under PPP model

Hanoi to build Tran Hung Dao Bridge under PPP model

The bridge is scheduled for completion by 2027 with an estimated total investment of VND16.2 trillion (US$615 million).

Hanoi launches seven major infrastructure projects to reshape urban growth and connectivity

Hanoi launches seven major infrastructure projects to reshape urban growth and connectivity

The projects, spanning urban renewal, transport, sports and social housing, underscore Hanoi’s ambition to build a modern, connected and livable city while contributing to national growth momentum.

Air pollution control in Hanoi hinges on correct diagnosis, experts warn

Air pollution control in Hanoi hinges on correct diagnosis, experts warn

Air quality must be viewed as a long-term and costly challenge rather than a problem that can be solved quickly.

Noi Bai International Airport expands terminal T2 to ease congestion, boost capacity

Noi Bai International Airport expands terminal T2 to ease congestion, boost capacity

The Hanoi-based airport has officially completed the expansion of Terminal T2, raising passenger capacity and rolling out advanced digital systems to ease congestion and improve service ahead of peak holiday travel.

Design of To Lich River Park highlights Hanoi's ecology and culture

Design of To Lich River Park highlights Hanoi's ecology and culture

The riverside park project is expected to become a green belt that helps restore ecosystems and improve living conditions for the capital.

Historic pottery exhibition traces shared cultural journey from Thang Long to Phu Xuan

Historic pottery exhibition traces shared cultural journey from Thang Long to Phu Xuan

A new thematic exhibition in Hanoi brings together centuries-old pottery from the former capitals of Thang Long and Phu Xuan, highlighting shared cultural roots and the enduring legacy of Vietnam’s ceramic traditions.

Hanoi artists promote eco-friendly art experiences for children

Hanoi artists promote eco-friendly art experiences for children

Unlike academic classes that are heavily focused on technique, Malena's Dream Canvas encourages spontaneity in creativity to nurture and protect the soul, also known as art in sanctuary, where each person is allowed to explore, share, heal and live fully with their passion.

Vietnam moves toward mandatory digital traceability for textile products

Vietnam moves toward mandatory digital traceability for textile products

Experts believe that each product needs a "digital passport" containing all production information for traceability, not just a label.