Chinese contractor demands extra US$50 million to operate Hanoi’s first metro line

Vietnam's Ministry of Transport will organize meetings with the Chinese contractor to discuss the capital issue for the trial operation of Hanoi’s first metro line.

While the completion date of the Cat Linh-Ha Dong urban railway project in Hanoi remains unknown, the general contractor of the project has requested a down payment of US$50 million for the system operation before handing over the project, local media reported.

The Hanoi Metropolitan Railway Management Board (MRB) has reported the issue to the Ministry of Transport, noting that the payment must comply with the regulations of the engineering procurement and construction contract.

 The inauguration date of Cat Linh-Ha Dong urban railway is nowhere in sight. Photo: Pham Hung

“The two sides have agreed to review the provisions of the contract within 15 days and hold a meeting to discuss the pending works,” the MRB noted.

The railway line is one of the key public transport projects in Hanoi. Since September 2018, its rolling stock of 13 trains has been tested, with the average speed of 35 kilometers per hour.

The railway is 13.5 kilometers long from Cat Linh Station in downtown Dong Da district to Yen Nghia Station in the southwestern Ha Dong district, and uses standard-gauge rail track (1,435mm).

Project costs have more than doubled from the original VND8.8 trillion (US$553 million) to VND18 trillion (US$868 million), according to state auditors, applying the exchange rate at their respective timings.

Work on the project began in October 2011, and the railway was initially scheduled to be put into commercial operation in 2015.

The railway is basically complete but is yet to be put into operation due to problems related to technical equipment at the depot, the safety assessment of trains, and final settlement of the contract and payment.

In February, over 100 Chinese experts were unable to return to Vietnam due to the Covid-19 pandemic, delaying the trial operation of the railway. However, on April 24, the Vietnamese government agreed to allow the entry of five experts working on the project.

The MRB has asked the Chinese contractor to complete the as-built documents and inspection dossiers for components such as the technical equipment, design of stations and depot.

Regarding the system safety certification, the MRB will work with the French consultancy Apave-Certifier-Tricc (ACT) and the Chinese contractor to complete it in line with the laws in Vietnam.

According to the government, the completion date for the project has not yet been decided and the responsibilities of organizations and individuals for the slow progress have not been made clear; so, funding has not been allocated for the construction supervision package.

To address these obstacles, the MRB suggested that the Ministry of Transport report the issues to the government for guidance, extend the construction supervision package, and organize meetings with the Chinese contractor to discuss capital demand for the trial operation of the railway.

Reactions:
Share:
Trending
Most Viewed
Related news
Hanoi commits US$230 million to curb urban flooding

Hanoi commits US$230 million to curb urban flooding

Emergency construction orders are essential to address urgent needs, including water pollution control, a stable, clean water supply, increased flows for the To Lich River and improved urban landscapes and living conditions.

Hanoi gears up for a vibrant 2026 Countdown

Hanoi gears up for a vibrant 2026 Countdown

With the energy of thousands gathering in Hanoi downtown, the Countdown 2026 promises to be an unforgettable way for people to welcome the New Year.

Hanoi launches AI-powered traffic control center for traffic violations

Hanoi launches AI-powered traffic control center for traffic violations

The system automatically detects common violations, significantly reducing the need for traffic police to be deployed directly on the streets while improving accuracy and transparency in traffic management.

Hanoi plans 10,000-hectare urban megacity with world-class stadium

Hanoi plans 10,000-hectare urban megacity with world-class stadium

The stadium’s design draws inspiration from Dong Son bronze drums and the Lac bird motif, symbolizing Vietnam’s aspiration to rise.

Hanoi greenlights Olympic sports city and Red River boulevard to drive next growth phase

Hanoi greenlights Olympic sports city and Red River boulevard to drive next growth phase

The approval of two landmark projects underscores Hanoi’s push to unlock new growth engines, reshape its urban structure and accelerate its ambition to become a green, smart and globally connected capital.

Hanoi targets 1,200 supporting industry firms by 2030

Hanoi targets 1,200 supporting industry firms by 2030

The city aims to enhance the competitiveness of the capital’s industrial sector by tightening cooperation with Vietnamese enterprises and multinational corporations operating in Vietnam.

Red River Boulevards shape Hanoi’s new growth axis

Red River Boulevards shape Hanoi’s new growth axis

The creation of a landscape boulevard can help Hanoi reconnect with its historic identity shaped by water and restore the river-based character that defined the city for centuries.

Hanoi moves to strengthen urban order and civility

Hanoi moves to strengthen urban order and civility

These include expanding public communication efforts, reorganizing and upgrading streets and sidewalks, maintaining a clean and orderly urban environment and carrying out strict inspections to address violations.