Hanoi addresses bottlenecks in public investment

Hanoi’s authorities are working with related parties to ensure the completion of public projects as scheduled.

The Hanoi People’s Committee is urging departments and districts to focus on accelerating public investment, seen as a key task to boost for socio-economic recovery.

 Le Van Luong underpass is scheduled for completion in October. Photo: Pham Cong

At the end of June, Hanoi disbursed only 21.2% of the annual allocation. A report from the local authorities attributed the unexpectedly low rate to a range of issues, including notable difficulties in the site clearance process.

According to the authorities, many projects are facing delays due to the complicated process to identify the origin of the lands and the subsequent land valuation process, while in some cases, the locals do not agree with the compensation packages.

Meanwhile, persisting issues have not been fully addressed, including the ineffective cooperation among Government agencies and cumbersome administrative procedures.

The Covid-19 pandemic impacts and rising prices of construction materials have also contributed to the issue, noted the report.

To ensure the realization of the public investment plan for the 2021-2025 period, Vice Chairman of the Hanoi People’s Committee Le Hong Son called for greater responsibilities from related parties in public investment projects, asking for each agency to submit a disbursement plan with a clear timeline on monthly – and quarterly basis to the city’s leaders.

“Leaders of units, departments, and localities are responsible for the progress of public projects,” Son said.

The city’s leader also expected agencies to speed up investment procedures, especially in project approval and modification.

In addition, Hanoi has been working with the Ministry of Construction to ensure a sufficient supply of construction materials, along with revising existing regulations on site clearance and supporting affected households in resettlements.

The city’s Vice Chairman asked all departments and units to review the priority order of projects in the 2021-2025 period for the arrangement of funds accordingly.

For the 2021-2025 period, the city sets to earmark VND650 trillion ($28.4 billion) for the public investment plan.

The priority order for investment would be aligned with the vision for the development of the transport sector and socio-economic infrastructure, namely ring road No.2.5, ring road 3, ring-road 3.5, ring road 4; major bridges crossing the rivers (Vinh Tuy bridge Phase 2, Thuong Cat bridge); inter-provincial roads (national road 6, upgrading national road 32, national road 1A, 21B); and urban railway projects.

Reactions:
Share:
Trending
Most Viewed
Related news
Hong Van Commune rises as Hanoi’s emerging model for community-based tourism

Hong Van Commune rises as Hanoi’s emerging model for community-based tourism

Blessed with natural beauty, strengthened by deep cultural heritage and supported by its residents, Hong Van Village is emerging as one of Hanoi’s most distinctive tourism destinations. From ecology and agriculture to handicrafts and festivals, this Red River village is shaping a dynamic vision of sustainable community tourism for the capital.

Hanoi unveils digital heritage journeys to connect tradition with modern urban life

Hanoi unveils digital heritage journeys to connect tradition with modern urban life

Hanoi has launched a new digital heritage program that brings centuries-old cultural assets into a modern, interactive format. By mapping key monuments and creating themed journeys, the city aims to help residents and visitors explore its deep-rooted identity through fresh, engaging experiences.

Hanoi launches two-wheel electric vehicles to expand green urban mobility

Hanoi launches two-wheel electric vehicles to expand green urban mobility

Hanoi has introduced two-wheel electric vehicles for the first time in its transport network, offering residents a new green mobility option and marking a key step in the city’s smart-transport development.

Thai AirAsia launches new Hanoi–Luang Prabang route to boost regional travel

Thai AirAsia launches new Hanoi–Luang Prabang route to boost regional travel

Thai AirAsia has opened a new direct Hanoi–Luang Prabang route using Fifth Freedom traffic rights, creating a faster and more convenient link between two major heritage destinations in Vietnam and Laos.

Hanoi orders strong air-pollution measures and warns schools to adjust schedules

Hanoi orders strong air-pollution measures and warns schools to adjust schedules

Hanoi has issued new directives requiring schools to restrict outdoor activities and consider suspending classes when air quality drops to hazardous levels, while launching a sweeping crackdown on pollution sources across the city.

Hanoi – Vientiane ties set pace for bilateral cooperation

Hanoi – Vientiane ties set pace for bilateral cooperation

The two sides have inked two city-level agreements and eight agreements covering areas such as Party building, economic and investment cooperation, agriculture, health, education and people-to-people ties.

Hanoi completes tunneling for four underground stations of 2nd metro line

Hanoi completes tunneling for four underground stations of 2nd metro line

The completion marks a major step forward for the four-kilometer underground section of the metro line.

Rooftop solar push to boost Hanoi's green ambition

Rooftop solar push to boost Hanoi's green ambition

Rooftop solar in industrial zones has the foundations to become a new driver of Hanoi’s energy transition.