Nhon – Hanoi Station metro line ready for test run in December

The elevated section of the Nhon-Hanoi Station metro line will officially undergo a test run in early December.

The Board of Directors of Hanoi Urban Railways (MRB) on November 23 announced the testing of the elevated section of the 8.5-kilometer Nhon-Hanoi station line.

The photo shows the Nhon Depot, the terminal of the Nhon-Hanoi Station urban railway project. Photo: The Hanoi Times 

The test, which will begin on December 5, is divided into two phases. The first, which will last between five days and six weeks, will test the efficiency of the line's reliability, availability, and maintainability (RAM).

According to the project management board, four to eight trains will be tested daily from 9 am to 7 pm on five consecutive days.

If RAM efficiency results are below 98%, the project management board will continue the test until the indicators meet the expected levels.

The second phase begins once the RAM efficiency is accepted. In the second phase, the metro line will go through five scenarios: a total power outage on the line, partial power interruption on the line, a secondary power source outage, detection of a fire in the station, and emergency vehicle operation.

Systra, the French mobility engineering and consulting group, requested that at least 22 Hanoi Urban Railway Management Board employees join the test, including a minimum of 22 drivers, five operational command center officers, and two managers.

The Nhon – Hanoi station metro project, with financial backing from the French Government, the French Development Agency (AFD), and the European Investment Bank (EIB), has a total length of 12.5 kilometers, running through eight elevated and four underground stations.

The project was initiated in September 2010. Due to issues in land clearance and financial capacity, the project's total investment has doubled to VND34 trillion (US$1.45 billion).

By the end of October 2022, the project was 75% complete, and the elevated lines were almost finished. By the end of August 2022, the total state budget disbursement for the project amounted to VND17 trillion.

The related parties expect the elevated portions to enter commercial operation in 2023. The 4-kilometer subway lines could be operational by the end of 2027.

Reactions:
Share:
Trending
Most Viewed
Related news
Vietnam news in brief - April 23

Vietnam news in brief - April 23

Update the latest news in Vietnam with The Hanoi Times.

Open Science and Technology Forum in operation on iHanoi

Open Science and Technology Forum in operation on iHanoi

One of the distinguishing features of the forum is the two-way interaction mechanism between people and managing agencies.

Hanoi may limit gasoline cars via draw or auction

Hanoi may limit gasoline cars via draw or auction

Only with careful preparation and a balanced approach can Hanoi tackle its pollution problems while ensuring that its residents have access to the mobility options they need.

Hanoi approves design for another bridge over Red River 

Hanoi approves design for another bridge over Red River 

The Ngoc Hoi Bridge will complete Hanoi's Ring Road 3.5, easing congestion, reducing accidents, and enhancing connectivity with the northern province province of Hung Yen.

Hanoi's typical heritage promoted through digitalized services

Hanoi's typical heritage promoted through digitalized services

Three prominent relics of Hanoi are available for digital tourism, in which tourists can scan NFC codes to learn more about the destination.

Hanoi Pho Festival: Pho cuisine in digital age

Hanoi Pho Festival: Pho cuisine in digital age

Taking place from April 18 to 20 at Thang Long Imperial Citadel, Pho Festival 2025 gathers more than 50 booths of businesses and pho brands across the country.

Vietnam news in brief - April 19

Vietnam news in brief - April 19

Update the latest stories in Vietnam with The Hanoi Times.

Pho Festival 2025 celebrates national culinary icon

Pho Festival 2025 celebrates national culinary icon

Pho Festival 2025 unites leading chefs and pho vendors from across Vietnam, offering visitors a unique culinary experience enhanced by AI technology.