Nhon – Hanoi Station metro line ready for test run in December

The elevated section of the Nhon-Hanoi Station metro line will officially undergo a test run in early December.

The Board of Directors of Hanoi Urban Railways (MRB) on November 23 announced the testing of the elevated section of the 8.5-kilometer Nhon-Hanoi station line.

The photo shows the Nhon Depot, the terminal of the Nhon-Hanoi Station urban railway project. Photo: The Hanoi Times 

The test, which will begin on December 5, is divided into two phases. The first, which will last between five days and six weeks, will test the efficiency of the line's reliability, availability, and maintainability (RAM).

According to the project management board, four to eight trains will be tested daily from 9 am to 7 pm on five consecutive days.

If RAM efficiency results are below 98%, the project management board will continue the test until the indicators meet the expected levels.

The second phase begins once the RAM efficiency is accepted. In the second phase, the metro line will go through five scenarios: a total power outage on the line, partial power interruption on the line, a secondary power source outage, detection of a fire in the station, and emergency vehicle operation.

Systra, the French mobility engineering and consulting group, requested that at least 22 Hanoi Urban Railway Management Board employees join the test, including a minimum of 22 drivers, five operational command center officers, and two managers.

The Nhon – Hanoi station metro project, with financial backing from the French Government, the French Development Agency (AFD), and the European Investment Bank (EIB), has a total length of 12.5 kilometers, running through eight elevated and four underground stations.

The project was initiated in September 2010. Due to issues in land clearance and financial capacity, the project's total investment has doubled to VND34 trillion (US$1.45 billion).

By the end of October 2022, the project was 75% complete, and the elevated lines were almost finished. By the end of August 2022, the total state budget disbursement for the project amounted to VND17 trillion.

The related parties expect the elevated portions to enter commercial operation in 2023. The 4-kilometer subway lines could be operational by the end of 2027.

Reactions:
Share:
Trending
Most Viewed
Related news
Discipline and professionalism to guide Hanoi success in 2026: Hanoi Party Secretary

Discipline and professionalism to guide Hanoi success in 2026: Hanoi Party Secretary

As the Lunar New Year of the Horse 2026 arrives, Hanoi glows with flags and flowers and steps into the new year with renewed confidence. Drawing on its heroic legacy and thousand-year cultural heritage, the capital aims to spearhead national development, advance innovation under the 14th National Party Congress Resolution and pioneer new growth models for a prosperous and modern future. Below is an article by Politburo member and Hanoi Party Secretary Nguyen Duy Ngoc outlining the capital’s key priorities for 2026.

All aboard for a Hanoi-Bac Ninh spring journey through memory and heritage

All aboard for a Hanoi-Bac Ninh spring journey through memory and heritage

This spring, The Hanoi Train’s “Bringing Spring Home” transforms a rail trip from Hanoi to Bac Ninh into a rich cultural journey, where travelers savor traditional Tet flavors, enjoy live folk performances and explore historic Ly Dynasty landmarks in a slow and immersive experience.

Lunar New Year greetings letter of Hanoi Party Secretary Nguyen Duy Ngoc

Lunar New Year greetings letter of Hanoi Party Secretary Nguyen Duy Ngoc

On the occasion of the Lunar New Year of the Horse 2026, Politburo member and Hanoi Party Secretary Nguyen Duy Ngoc sent greetings to officials, residents and soldiers of the capital, as well as Hanoians across the country and abroad. Below is the full text of his New Year letter:

Hanoi’s sky ablaze with New Year fireworks

Hanoi’s sky ablaze with New Year fireworks

At exactly midnight on the first day of the 2026 Lunar New Year, vibrant fireworks lit up the capital’s sky, drawing cheers and applause from crowds who welcomed the moment with joyful excitement and heartfelt wishes for a prosperous year ahead.

Party General Secretary offers incense for national peace in Hanoi

Party General Secretary offers incense for national peace in Hanoi

Praying for national peace and stability, the delegation voiced confidence that the country will enter a new era of development marked by stronger achievements, prosperity and greater well-being.

Hanoi affirms leadership role in new era of national development: Municipal Party Chief

Hanoi affirms leadership role in new era of national development: Municipal Party Chief

The mettle, intellect and stature of a cultured and heroic Hanoi will remain a steady anchor as the capital writes new pages in the country’s next stage of development.

Party Chief To Lam pays tribute to ancestors at Thang Long Citadel

Party Chief To Lam pays tribute to ancestors at Thang Long Citadel

The Party chief expresses deep respect and gratitude to past emperors who helped build and defend the nation.

All-night buzz at Quang An Flower Market ahead of Tet

All-night buzz at Quang An Flower Market ahead of Tet

In the days leading up to the Lunar New Year, Quang An Flower Market in Hong Ha Ward, Hanoi, becomes a vibrant portrait of spring in the capital. From late evening until dawn, crowds of residents pack the market, bustling to buy flowers for Tet celebrations.