Elevated section of Hanoi’s French-funded metro line to be soon completed
Hanoi’s metro line 3 runs 8.5 kilometers on elevated tracks through eight stations and four kilometers underground through four stations.
The construction of the elevated section the Nhon – Hanoi Railway Station sky train, also known as Hanoi’s metro line 3, is being accelerated to put it into operation in April 2021, Kinh Te & Do Thi newspaper quoted a leader of the Hanoi Metropolitan Railway Board (MRB) as saying.
According to the MRB, the packages for the elevated section are in due progress. Specifically, the CP01 package has been completed 100%, the CP02 package has 71.3% of the volume fulfilled, the CP05 package has reached 58.22%.
Workers conduct three shifts per day at the Nhon - Hanoi Railway Station project. Photo: Ngoc Hai |
Deputy Head of the MRB Le Trung Hieu affirmed that construction progress of the items related to electricity, information supplying and signaling will be ensured and the elevated section will become operational in April 2021.
"We will strive to bring the first trains to Vietnam in July to prepare for trial operation," Hieu said.
Under the plan, the elevated section of the metro line, which also include an underground section, will be put into operation first.
Immediately after Tet holiday, from February 3, construction of the Nhon – Hanoi Railway Station has resumed with three shifts per day, employing 836 people who are regularly present at the project.
In November, a Tunnel Boring Machine (TBM) will start digging the underground section.
Construction of this project was started on October 10, 2010. According to the MRB, the project’s first 8.5 km of the elevated tracks is set to be inaugurated in April 2021, then 4 km of the underground section is scheduled for completition in December 2022 and the entire line is expected to become operational by that time.
The total cost of the project has been revised up to EUR1.176 billion. Of which, EUR178.7 million comes as ODA provided by the French Development Agency (AFD) and EUR355.1 million as loan from the French government.
It is one of several metro lines planned for the capital city to ease traffic congestion and reduce emissions.
Other News
- Hanoi's socio-economic and cultural achievements on display
- Thang Long Imperial Citadel celebrates Capital Liberation with a host of activities
- "Cultural Festival for Peace": Historic takeover of Hanoi
- Hanoi’s thousands-year tradition valuable for development: Mayor
- Cultural Festival for Peace to promote Hanoi as a peaceful destination
- INWES – APNN 2024 Conference attracts hundreds of intellectuals from 13 countries to Hanoi
- Old Hanoi space comes alive with 'Memories of Hanoi - 70 Years' exhibition
- Special TV programs for Hanoi Liberation Day
- Touching Hanoi's memories with concert 'Phu Quang - Love Remains'
- Digital transformation essential to Hanoi urban planning: Experts
Trending
-
"Cultural Festival for Peace": Historic takeover of Hanoi
-
Hanoi’s thousands-year tradition valuable for development: Mayor
-
Prime Minister Pham Minh Chinh attends “Cultural Festival for Peace” in Hanoi
-
Cultural Festival for Peace to promote Hanoi as a peaceful destination
-
Vietnam condemns violence by Chinese authorities in Hoang Sa
-
All Vietnamese citizens to have electronic health records: PM
-
Digital transformation essential to Hanoi urban planning: Experts
-
Join hands to build a civilized, modern capital: Experts
-
Hanoi’s child elected to "Children Parliament"