Hanoi announces action plan on Ring-road No.4 implementation

The action plan set the timeline until the end of September 2022 for the authorities of three provinces/cities of Hanoi, Hung Yen, and Bac Ninh to set up a Steering Committee to oversee the project implementation.

Hanoi is expected to start the construction works for the Ring-road No.4 in June 2023, and  put it into operation in 2027.

 A 3D design of conjunction under Ring road No.4. File photo

The timeline was revealed in the city’s action plan No.244/KH-UBND, signed off by the Chairman of the Hanoi People’s Committee Tran Sy Thanh, on the implementation of the project, designed to bolster inter-provincial linkage between Hanoi and other provinces/cities in the Hanoi Capital Zone.

Ring road No.4 would run 112.8 kilometers  through Hanoi (58.2 kilometers), Hung Yen (19.3 kilometers), and Bac Ninh (25.6 kilometers), covering a combined area of 1,341 hectares.

Under the action plan,  the project will be divided into sub-components including site clearance and resettlement for affected households; construction of an urban road; and investment in the highway under the public-private partnership (PPP).

The Hanoi People’s Committee plans to hand over at least 70% of the construction site to contractors in June 2023 and complete the work in December.

This would help the construction to start in June 2023, and basically be completed in 2026, before being put into operation in 2027.

The municipal People's Committee assigned Soc Son, Me Linh, Hoai Duc, Dan Phuong, Thanh Oai and Thuong Tin districts to finish reviewing in April 2023 the relocation demand and cooperate with local authorities in carrying out the construction of resettlement areas.

The action plan set the timeline until the end of September 2022 for the authorities of  Hanoi, Hung Yen, and Bac Ninh to set up a Steering Committee to oversee the project implementation upon instruction from the Government.

The Hanoi Transportation Construction Project Management Unit is tasked with completing the project boundary demarcation by September 2022.

The selection  for contractors  should start in late December 2022 and be completed by June 2023.

The total investment cost of the project is VND85.8 trillion ($3.7 billion), with VND41.8 trillion ($1.8 billion) for the 2021-2025 period sourced from the state budget. Of the total, Hanoi would contribute VND22.47 trillion ($967.2 million) from its local budget, Hung Yen VND1 trillion ($43 million), and Bac Ninh VND2 trillion ($86 million).

In the subsequent five years, the project funding would continue to be allocated VND14.5 trillion ($624.2 million), with Hanoi contributing VND4 trillion ($172 million), Hung Yen VND505 billion ($21.7 million), and Bac Ninh VND1.16 trillion ($50 million).

The private sector, meanwhile, is expected to fund VND29.4 trillion ($1.26 billion).

Reactions:
Share:
Trending
Most Viewed
Related news
Hanoi health sector targets digital leap under new Party resolution

Hanoi health sector targets digital leap under new Party resolution

Hanoi sets 2026 as a breakthrough year for healthcare reform, accelerating digital transformation, restructuring hospital networks and tightening food safety management under Politburo Resolution 72.

Hanoi launches state-backed innovation hub to drive digital economy

Hanoi launches state-backed innovation hub to drive digital economy

The new innovation center is designed to connect policy, technology and talent, aiming to accelerate digital transformation, support startups and position the capital as a global testing hub for emerging technologies and creative industries.

ASEAN youth showcase climate innovations at Hanoi exhibition

ASEAN youth showcase climate innovations at Hanoi exhibition

Young innovators from Vietnam and across ASEAN presented practical climate solutions in Hanoi, highlighting grassroots initiatives tackling plastic waste, renewable energy and sustainable livelihoods.

Hanoi issues action plan to implement 14th Party Congress resolution

Hanoi issues action plan to implement 14th Party Congress resolution

The goal is to turn policies into outcomes under the principle of “less talk, more action, effective results to the end, all for the capital and its people.”

ASEAN youth chart next phase of climate action in Hanoi

ASEAN youth chart next phase of climate action in Hanoi

Home to more than 680 million people, many in vulnerable coastal and low-lying areas, ASEAN is on the front line of climate change, facing rising seas, fiercer storms, prolonged droughts and accelerating biodiversity loss that endanger the region’s economic resilience and social stability.

Hanoi launches sweeping overhaul to unlock state economy growth

Hanoi launches sweeping overhaul to unlock state economy growth

Hanoi has unveiled an ambitious five-year plan to reform governance, mobilize public assets and restructure state enterprises, aiming to turn the state economy into a powerful engine of sustainable growth.

Hanoi puts people first in implementing four strategic Party resolutions

Hanoi puts people first in implementing four strategic Party resolutions

Hanoi launches comprehensive action plans to implement Politburo Resolutions 71, 72, 79 and 80, prioritizing people-centered reforms in education, healthcare, culture and state economic development.

Vietnamese families blend Tet travel trends with enduring traditions

Vietnamese families blend Tet travel trends with enduring traditions

More young Vietnamese families choose travel over staying home during the Lunar New Year holiday, seeking fresh experiences while keeping core traditions intact.