Hanoi's authorities are requested to spend more time handling the remaining issues, especially, the safety of the Cat Linh-Ha Dong urban railway.
The Ministry of Transport will strive to complete safety evaluation and hand over to Hanoi’s authorities the Cat Linh-Ha Dong route urban railway project, the first of its kind in the city, by late December, Kinh Te & Do Thi quoted Minister of Transport Nguyen Van The as saying at a governmental meeting on October 28.
The minister said around ten French experts in charge of the safety assessment of Cat Linh-Ha Dong urban railway project would tentatively arrive in Hanoi by mid-November.
Meanwhile, China Railway Sixth Group, the EPC contractor, will try to complete the conditional acceptance for the metro line and the Ministry of Transport will make every effort to put the project into commercial operation before the National Party Congress begins, scheduled to take place in the first quarter of 2021, Mr. The said.
Test run has been conducted on Cat Linh-Ha Dong urban railway since March 2019. Photo: Kinhtedothi.vn |
He added that the Chinese contractor has imported 99% of equipment needed for the project, and their installation is now 97% complete. However, the contractor has not provided all safety certificates for equipment installed and the consortium tasked with safety evaluation has not been able to complete the job.
The Ministry of Transport has proposed that the consortium, comprised of French firms Apave, Certifier and Tricc, grant the project a temporary safety certificate so it can start commercial operations soon.
Apave-Certifier-Tricc said earlier this month that a complete evaluation could take another six months, which means the line will not become operational until next year, even though Prime Minister Nguyen Xuan Phuc has set a year-end deadline.
PM Phuc suggested that ministries and Hanoi city must spend more time handling the remaining issues, especially, the safety of the Cat Linh-Ha Dong urban railway, which is a political task that the investor and Hanoi city must attach special importance to.
Work on the Cat Linh-Ha Dong metro line began in 2011 and was originally scheduled for completion in 2013. But several hurdles, including loan disbursement issues with China that were only resolved in December 2017, have stalled it for years.
The line eventually entered the testing phase in March with all 13 cars carrying out trial runs on both lines. The ministry wanted commercial operations to begin at the end of April, but this deadline too was missed.
Project costs have more than doubled from the original VND8.8 trillion (US$378 million) to VND18 trillion (US$774 million), according to state auditors.
The line now has 1% work remaining, mainly exterior finishing. When complete, the country’s first metro line will run 13 kilometers from Cat Linh station in downtown Dong Da district to Yen Nghia station in southwest Ha Dong district.
Other News
- Hanoi welcomes 740,000 visitors for Reunification Day and May Day
- Hanoi focuses on cultural and historical tourism
- Record late April heat scorches Hanoi
- Hanoi’s integral role in national unification drive
- 20 new FDI projects set up in April in Hanoi
- Introduction of community tourism area in Hanoi herb kingdom
- Photo exhibition commemorates Vietnamese people's glorious victories
Trending
-
Tran Thanh Man assigned to drive National Assembly activities
-
Vietnam news in brief - May 3
-
Four- and five-star hotels to boom in Hanoi as tourism rebounds
-
Trivial jobs: Hanoians strive to keep their old trades alive
-
Hanoi strives to ensure smooth high school exams
-
Carnaval Ha Long 2024 woos tourists with fireworks and drone light shows
-
Affordable, quality tours offered at Hanoi Tourism Festival 2024
-
Introduction of community tourism area in Hanoi herb kingdom
-
Capital Law revision helps Hanoi promote role as nation’s socio-economic hub