Hanoi's authorities are requested to spend more time handling the remaining issues, especially, the safety of the Cat Linh-Ha Dong urban railway.
The Ministry of Transport will strive to complete safety evaluation and hand over to Hanoi’s authorities the Cat Linh-Ha Dong route urban railway project, the first of its kind in the city, by late December, Kinh Te & Do Thi quoted Minister of Transport Nguyen Van The as saying at a governmental meeting on October 28.
The minister said around ten French experts in charge of the safety assessment of Cat Linh-Ha Dong urban railway project would tentatively arrive in Hanoi by mid-November.
Meanwhile, China Railway Sixth Group, the EPC contractor, will try to complete the conditional acceptance for the metro line and the Ministry of Transport will make every effort to put the project into commercial operation before the National Party Congress begins, scheduled to take place in the first quarter of 2021, Mr. The said.
Test run has been conducted on Cat Linh-Ha Dong urban railway since March 2019. Photo: Kinhtedothi.vn |
He added that the Chinese contractor has imported 99% of equipment needed for the project, and their installation is now 97% complete. However, the contractor has not provided all safety certificates for equipment installed and the consortium tasked with safety evaluation has not been able to complete the job.
The Ministry of Transport has proposed that the consortium, comprised of French firms Apave, Certifier and Tricc, grant the project a temporary safety certificate so it can start commercial operations soon.
Apave-Certifier-Tricc said earlier this month that a complete evaluation could take another six months, which means the line will not become operational until next year, even though Prime Minister Nguyen Xuan Phuc has set a year-end deadline.
PM Phuc suggested that ministries and Hanoi city must spend more time handling the remaining issues, especially, the safety of the Cat Linh-Ha Dong urban railway, which is a political task that the investor and Hanoi city must attach special importance to.
Work on the Cat Linh-Ha Dong metro line began in 2011 and was originally scheduled for completion in 2013. But several hurdles, including loan disbursement issues with China that were only resolved in December 2017, have stalled it for years.
The line eventually entered the testing phase in March with all 13 cars carrying out trial runs on both lines. The ministry wanted commercial operations to begin at the end of April, but this deadline too was missed.
Project costs have more than doubled from the original VND8.8 trillion (US$378 million) to VND18 trillion (US$774 million), according to state auditors.
The line now has 1% work remaining, mainly exterior finishing. When complete, the country’s first metro line will run 13 kilometers from Cat Linh station in downtown Dong Da district to Yen Nghia station in southwest Ha Dong district.
Other News
- More flyovers to ease traffic congestion in Hanoi
- Hanoi's relics draw visitors from near and far this Tet 2025
- Hanoi makes strides in traffic management
- Hanoi to train 240,000 workers in 2025
- Resolution 57 sparks reforms to strengthen Vietnam's science and technology sector
- Tet through the eyes of overseas students
- General Secretary To Lam sends Lunar New Year greetings to Hanoi’s Party, authorities and people
- Hanoi upholds role as Vietnamese capital: Bui Thi Minh Hoai, Secretary of the Hanoi Party Committee
- Hanoi metro lines to run non-stop during Tet 2025
- Hanoi accelerates efforts to promote sustainable transportation
Trending
-
Dong Da Mound Festival: Celebration of heroic tradition
-
Admiring Dong Ho folk paintings on traditional ao dai
-
The 45 snake sculptures – unique masterpieces celebrate the Year of the Snake
-
Tet through the eyes of overseas students
-
Hanoi promotes urban decorations for Tet
-
Vietnam hosts first international lantern competition
-
Hanoi kicks off the Spring Calligraphy Festival in celebration of Lunar New Year
-
Hanoi’s central role means heightened responsibility in foreign affairs: Mayor
-
Hanoi revives historic Tet traditions in Duong Lam Ancient Village