14TH NATIONAL CONGRESS OF THE COMMUNIST PARTY OF VIETNAM
Log in
Hanoi

Hanoi commits US$230 million to curb urban flooding

Emergency construction orders are essential to address urgent needs, including water pollution control, a stable, clean water supply, increased flows for the To Lich River and improved urban landscapes and living conditions.

THE HANOI TIMES — The Hanoi Department of Construction has proposed the issuance of 10 emergency construction orders with an estimated investment of VND5.5 trillion (US$232 million) to swiftly address urban flooding citywide.

Road 70 near Nga Bridge in Xuan Phuong Ward, Hanoi, was deeply flooded during the 2025 rainy season. Photo: Quy Nguyen/The Hanoi Times

In recent months, Hanoi has experienced widespread and prolonged flooding caused by storms.

Post-storm flooding has had severe impacts, including major traffic disruption as many roads were deeply inundated, leading to prolonged congestion and vehicle damage.

It has also seriously affected daily life by restricting movement, isolating residential areas and causing significant property and economic losses.

Severe flooding has resulted from fragmented and delayed investment in drainage systems and key discharge infrastructure. Of the inner-city area of about 313.19 square kilometres, only around 77.5 square kilometers within the To Lich basin are equipped with drainage systems, which accounts for just 24.7%.

Investment in discharge outlets and pumping stations has lagged. The required total capacity for the Ta Day area is 811.5 cubic meters per second, while the current urban drainage capacity is about 164.5 cubic meters per second, or 20%.

The Yen Nghia pumping station has a capacity of 120 cubic meters per second, but has not operated at full capacity. The constraints include a lack of regulating lakes, incomplete sections of the La Khe canal and limited discharge to the Day River during high water levels.

The Lien Mac headworks, with a capacity of 170 cubic meters per second, is under construction, while drainage for urban areas outside the inner city remains dependent on water levels in the Nhue River.

At the same time, regulating lakes approved under existing plans has not been implemented in a coordinated manner. The total planned area for regulating lakes is about 5,405 hectares, while the existing area is around 1,010 hectares or 18.7%.

Investment and management of drainage systems in some new urban areas have also lacked coordination.

Internal drainage networks have been built but are not fully connected to area-wide systems.

Ground elevations in newly developed areas are inconsistent with surrounding levels, and some developments sit lower than adjacent areas, causing rapid surface runoff during heavy rain and leads to localized flooding as discharge outlets and pumping stations have yet to be built.

To respond promptly to storm-related disaster risks, the city needs to strengthen drainage capacity and ensure effective system connectivity.

The municipal People’s Committee will strengthen oversight, prioritize investment resources and streamline procedures to keep projects on schedule. Main components are expected to be largely completed before the 2026 storm season.

Based on project scale and characteristics, the city has designated two implementing agencies: the Technical Infrastructure and Agricultural Construction Investment Project Management Board for seven projects and the Hanoi Technical Infrastructure Management Center for three projects.

These projects include:

  1. Upgrades, expansions and new drainage works to address flooding in the Resco, Ecohome, Tay Ho Tay, Diplomatic Corps, Ciputra, Vo Chi Cong, Long Bien, Dong Anh and Gia Lam areas, with a total estimated investment of VND262 billion ($11 million) and completion targeted for the second quarter of 2026.
  2. Upgrading the Thuy Phuong canal to urgently supplement water for the To Lich River and strengthen localized flood control in the Resco, Ecohome, Diplomatic Corps, Tay Ho Tay, Ciputra and surrounding areas, with an estimated investment of VND869 billion ($36 million) and expected completion in the third quarter of 2026, with main components finished before the 2026 rainy season.
  3. Upgrading the downstream Kim Nguu canal, linking the To Lich River to the Yen So pumping station, under a project valued at about VND700 billion ($29 million), is scheduled for completion in the third quarter of 2026, with key works finished ahead of the 2026 rainy season. 
  4. Increasing the capacity of existing pumping stations, installing temporary pumping stations and upgrading or building new drainage pipes and channels to address flooding along Thang Long Boulevard, with a total investment estimated at VND163 billion ($6.8 million) and completion planned for the second quarter of 2026. 
  5. Construction of the Phu Do regulating lake in Tu Liem Ward, with a total estimated investment of VND800 billion ($33 million) and scheduled for completion in the fourth quarter of 2026, with major components finished before the 2026 rainy season.
  6. Construction of the Yen Nghia 2 regulating lake in An Khanh Commune, with an estimated investment of VND250 billion ($10 million) and completion targeted for the fourth quarter of 2026, with main works completed ahead of the rainy season.
  7. Installation of additional pumping stations, regulating tanks and drainage pipelines in the To Lich and Ta Nhue basins, with a total estimated investment of VND590 billion ($25 million) and expected completion in the second quarter of 2026.
  8. Construction of the Thuy Phuong 2 regulating lake in Dong Ngac Ward, with an estimated investment of VND717 billion ($30 million) and scheduled for completion in the fourth quarter of 2026, with key components finished before the 2026 rainy season. 
  9. Construction of the Yen Nghia 1 regulating lake in An Khanh Commune, under a project valued at about VND858 billion ($36 million), is expected to be completed in the fourth quarter of 2026, with major works finalized ahead of the rainy season. 
  10. Construction of the Me Tri head regulating lake, also known as Dong Bong 2, in Dai Mo Ward, with a total estimated investment of VND370 billion ($15 million) and completion planned for the fourth quarter of 2026, with main components finished before the 2026 rainy season.

Reactions:
Share:
Trending
Most Viewed
Related news
Hanoi mobilizes relief convoy to aid flood-hit Central Highlands

Hanoi mobilizes relief convoy to aid flood-hit Central Highlands

26 Nov, 22:31

Hanoi’s efforts in the Central Highlands and Central Vietnam are not only acts of charity but also an enduring testament to the city’s humanitarian spirit, showing that in times of crisis, collective action and compassion can make all the difference.

Hanoi strengthens communication to promote Vietnamese goods in domestic market

Hanoi strengthens communication to promote Vietnamese goods in domestic market

Hanoi authorities are intensifying communication and outreach for the “Vietnamese people prioritize using Vietnamese goods” campaign, aiming to strengthen domestic production, boost consumer confidence and ensure Vietnamese products maintain a leading presence in the capital’s retail market.

Hanoi trade unions launch Tet markets with high-quality, affordable Vietnamese merchandises

Hanoi trade unions launch Tet markets with high-quality, affordable Vietnamese merchandises

Ahead of the Lunar New Year 2026, Hanoi’s trade unions are launching a series of welfare initiatives, including zero-dong booths and discounted Tet markets, to help workers purchase quality Vietnamese goods while reducing financial strain during the festive season.

Regional delicacies draw Tet buyers but face hurdles in Hanoi retail networks

Regional delicacies draw Tet buyers but face hurdles in Hanoi retail networks

Hanoi supermarkets expand Tet offerings of regional specialties, but stable supply, safety compliance and traceability remain critical challenges.

Hanoi’s craft villages find new life in the creative economy

Hanoi’s craft villages find new life in the creative economy

From village workshops to global showcases, Hanoi’s craft villages are reinterpreting tradition through creativity, turning cultural identity into economic value and strengthening domestic consumption at home and abroad.

Young voices carry confidence and responsibility as 14th National Party Congress begins

Young voices carry confidence and responsibility as 14th National Party Congress begins

At the opening of the 14th National Congress of the Communist Party of Vietnam, young delegates across Vietnam express confidence, responsibility and expectations for breakthrough policies shaping the nation’s next development phase.

Hanoi ready to lead 14th Party Congress vision

Hanoi ready to lead 14th Party Congress vision

Hanoi enters the 14th National Party Congress with renewed confidence after a year of major administrative reforms and strong economic gains, positioning the capital to play a pioneering role in implementing the congress’s new strategic directions nationwide

Work starts on US$612 million elderly healthcare complex in Hanoi

Work starts on US$612 million elderly healthcare complex in Hanoi

The complex project is designed as a multi-functional center with high-quality medical services, education and clinical training, scientific research and comprehensive elderly care.

Hanoi orders urgent action to tackle environmental pollution

Hanoi orders urgent action to tackle environmental pollution

Hanoi’s Party chief has called for urgent, comprehensive action to tackle environmental pollution, warning that delays are undermining urban sustainability and the city’s tourism appeal.