Hanoi's Party chief wants better solutions for Ring Road 1 project land clearance

The Ring Road 1 Project is now three years behind as it was scheduled to become operational in 2020.

Hanoi Party chief Dinh Tien Dung urged local authorities in Dong Da and Ba Dinh districts on April 5 to speed up land clearing so that the Ring Road 1 project can be completed next year.

Secretary of the Hanoi Party Committee Dinh Tien Dung (center) visits the Ring Road 1 project in Dong Da and Ba Dinh districts on April 4. Photo: Thanh Hai/The Hanoi Times

The Hanoi Party Committee Secretary stated during a tour of the Ring Road 1 construction site that the project's prolonged delay has resulted in cost overruns, impacted locals' quality of life, and jeopardized social security.

The 2.2-kilometer-long Ring Road 1 project connects Hoang Cau Street in Dong Da District with Voi Phuc Temple in Ngoc Khanh Ward, Ba Dinh District.

December 2017 saw the project kick-off, with an estimated capital of VND7.8 trillion (US$332.5 million), of which VND6.4 trillion (US$272.8 million) will be used for clearing land and VND627 billion (US$26.7 million) for construction. It was projected to be finished in 2020.

Dung said the project management unit must work with local authorities to study a feasible plan to compensate local people and help them resettle.

"We must give our people the best in land clearance and resettlement. Local authorities must also help people make a living," he said.

According to Dong Phuoc An, Director of the Public Infrastructure Construction Project Management Department, land clearance remains the biggest problem hindering the Ring Road 1 project.

He said that out of more than 2,000 families to be moved, about 440 households objected to the compensation and relocation plan.

According to Le Tuan Dinh, the head of the people's committee of Dong Da District, many families lack property entitlement documents, and "their houses were illegally constructed on state-owned property."

"The district authorities have offered the families a compensation plan, but they have been uncooperative," he added.

They won't receive compensation in line with market value and that, even with that payment, they won't be able to purchase new homes in the resettlement area," he said.

The head of the Ba Dinh District People's Committee, Ta Nam Chien, added that the district has frequently requested special financial aid from the local government for families who reject the compensation.

According to Duong Duc Tuan, Vice Chairman of the Hanoi People's Committee, the Department of Agriculture and Rural Development will research the precedents to create a new compensation plan for locals while city officials will review the compensation plan for these households.

Reactions:
Share:
Trending
Most Viewed
Related news
Hanoi launches digital job portal to boost labor matching

Hanoi launches digital job portal to boost labor matching

Hanoi has introduced a new digital platform designed to connect workers and employers more efficiently as the capital modernizes its labor market.

Hanoi’s 100-year master plan to shape the capital’s future growth

Hanoi’s 100-year master plan to shape the capital’s future growth

The planning must be of the highest quality so Hanoi can fully realize its distinctive potential, key opportunities and competitive advantages.

Hanoi opens 11th annual sports games celebrating unity, excellence, athletic spirit citywide

Hanoi opens 11th annual sports games celebrating unity, excellence, athletic spirit citywide

Hanoi opened the Capital Sports Games 2025 with a grand ceremony, highlighting the city’s growing sports movement, strong community participation and ambition to elevate both mass fitness and elite athletics.

Institutional breakthroughs as catalyst for Hanoi’s next leap

Institutional breakthroughs as catalyst for Hanoi’s next leap

The resolution not only empowers the city and speeds up processes but also outlines a more proactive and efficient model of urban governance for Hanoi’s future.

Hanoi commits US$230 million to curb urban flooding

Hanoi commits US$230 million to curb urban flooding

Emergency construction orders are essential to address urgent needs, including water pollution control, a stable, clean water supply, increased flows for the To Lich River and improved urban landscapes and living conditions.

Hanoi gears up for a vibrant 2026 Countdown

Hanoi gears up for a vibrant 2026 Countdown

With the energy of thousands gathering in Hanoi downtown, the Countdown 2026 promises to be an unforgettable way for people to welcome the New Year.

Hanoi launches AI-powered traffic control center for traffic violations

Hanoi launches AI-powered traffic control center for traffic violations

The system automatically detects common violations, significantly reducing the need for traffic police to be deployed directly on the streets while improving accuracy and transparency in traffic management.

Hanoi plans 10,000-hectare urban megacity with world-class stadium

Hanoi plans 10,000-hectare urban megacity with world-class stadium

The stadium’s design draws inspiration from Dong Son bronze drums and the Lac bird motif, symbolizing Vietnam’s aspiration to rise.