ODA disbursement hits 19% of target in Jan-Sep

The Covid-19 pandemic has significantly impacted the construction progress of public projects across the country.

Despite the strong efforts from government agencies, the disbursement rate of ODA (official development assistance) projects in the first nine months of 2021 stood at 19.03% of the plan.

 An overpass at the intersection of Nguyen Van Huyen and Hoang Quoc Viet street in Hanoi. Photo: Thanh Hai

Director of the Department of Debt Management and External Finance under the Ministry of Finance (MoF) Truong Hung Long said at an online conference held today [October 7].

According to Long, seven ministries and ministerial-level agencies reported a 0% disbursement rate, while nine others requested to return their entire allocated funds of VND8 trillion ($352.3 million), or 44.08% of total ODA funds this year.

“Such an amount may be transferred to agencies or localities in need of capital, or return to the central budget if no request arises,” Long said, while acknowledging it is unlikely to realize the goal of disbursing over 95% of the ODA funds this year.

Vice Director of the Department of Debt Management and External Finance Vo Huu Hien added this year, the Government allocated a total of VND51.5 trillion ($2.26 billion) in ODA funds, in which VND16.63 trillion ($732.5 million) went to ministries and VND35 trillion ($1.54 billion) to local governments.

Hien pointed out the serious Covid-19 situation in 19 provinces/cities, including major cities of Ho Chi Minh City, Hanoi, and Danang, which has directly impacted economic activities and the progress of public projects, forcing many to temporarily stop or preventing foreign consultants from entering Vietnam.

Other issues have also contributed to the delay in the construction progress, including the difficulties in site clearance, resettlement of affected households, slow progress in bidding procedures, or adjustment to financing agreement, Hien continued.

Hien called for greater efforts to accelerate the disbursement of ODA funds in areas with a low risk of infection to compensate for the delayed works at locations under lockdown.

The MoF, for its part, would closely cooperate with other agencies in speeding up the disbursement of public funds, including the ODA and preferential loans, Hien stressed.

Hien called for project owners to enhance efficiency in managing ODA projects and report any difficulties to competent authorities for timely address.

“It is essential for project owners to select qualified and capable consultants in project design to avoid potential modification in the execution,” he said.

In a recent meeting in early October, Deputy Prime Minister Pham Binh Minh suggested the Vietnamese Government is in process of drafting a new decree in replacement of decree No.56 on ODA management, with a view to both simplify the administrative process and ensure efficiency in the use of ODA.

Hanoi is among the cities that were hit hard by the fourth Covid-19 outbreak. The city, however, still posted a positive disbursed amount of ODA funds at VND3.66 trillion ($161 million) in the first nine months of 2021, or 46.7% of the yearly target and up 7.2% year on year.

The rate was significantly higher than that of the national average and showcased strong efforts from local authorities to speed up economic recovery, with public investment seen as a major solution to boost growth during the pandemic.

Reactions:
Share:
Trending
Most Viewed
Related news
Hanoi apartment market heads for major supply surge beginning in 2026

Hanoi apartment market heads for major supply surge beginning in 2026

Hanoi’s apartment market is entering a new growth phase with a strong supply wave expected from 2026 as major projects launch across all segments from social housing to high-end developments.

Two social housing projects offered for sale as Hanoi strives to meet mounting demand

Two social housing projects offered for sale as Hanoi strives to meet mounting demand

Hanoi launches sales for CT-05 and CT-06 social housing projects in Quang Minh Commune, offering low-cost units as the city faces rising housing pressure.

Vietnam creates National Housing Development Fund to boost social housing supply by 2030

Vietnam creates National Housing Development Fund to boost social housing supply by 2030

Vietnam has taken a major step toward expanding affordable housing by establishing the National Housing Development Fund, a new financial mechanism designed to accelerate social housing development and stabilize the property market.

Hanoi to see sharp jump in land prices under new 2026 pricing framework

Hanoi to see sharp jump in land prices under new 2026 pricing framework

The sharp increases raise concerns over affordability, investment risks and shifting market behavior as land values climb across diverse areas of the city.

Hanoi to launch $34 million canal project to curb flooding, revive To Lich River

Hanoi to launch $34 million canal project to curb flooding, revive To Lich River

Hanoi starts a $34-million project to upgrade Thuy Phuong Canal, improve drainage and restore To Lich River flow with completion expected by Q3/2026.

Hanoi greenlights sub-zone B of 16,000-hectare southern sports and housing project

Hanoi greenlights sub-zone B of 16,000-hectare southern sports and housing project

The sub-zone B is designed to be a complex containing sports facilities, housing, public services, schools and agricultural land, with an estimated accommodation of 250,000–285,000 residents.

Strong public participation to drive Hanoi’s sustainable and dynamic urban growth

Strong public participation to drive Hanoi’s sustainable and dynamic urban growth

Hanoi’s development depends on effective planning, mobilization of social resources and clear decentralization with accountability and transparency.

Hanoi housing prices surge sharply in Q3/2025 amid limited supply

Hanoi housing prices surge sharply in Q3/2025 amid limited supply

Hanoi apartment prices remained high in Q3/2025, rising sharply amid limited supply and growing affordability concerns.