The Covid-19 pandemic has significantly impacted the construction progress of public projects across the country.

Despite the strong efforts from government agencies, the disbursement rate of ODA (official development assistance) projects in the first nine months of 2021 stood at 19.03% of the plan.
An overpass at the intersection of Nguyen Van Huyen and Hoang Quoc Viet street in Hanoi. Photo: Thanh Hai |
Director of the Department of Debt Management and External Finance under the Ministry of Finance (MoF) Truong Hung Long said at an online conference held today [October 7].
According to Long, seven ministries and ministerial-level agencies reported a 0% disbursement rate, while nine others requested to return their entire allocated funds of VND8 trillion ($352.3 million), or 44.08% of total ODA funds this year.
“Such an amount may be transferred to agencies or localities in need of capital, or return to the central budget if no request arises,” Long said, while acknowledging it is unlikely to realize the goal of disbursing over 95% of the ODA funds this year.
Vice Director of the Department of Debt Management and External Finance Vo Huu Hien added this year, the Government allocated a total of VND51.5 trillion ($2.26 billion) in ODA funds, in which VND16.63 trillion ($732.5 million) went to ministries and VND35 trillion ($1.54 billion) to local governments.
Hien pointed out the serious Covid-19 situation in 19 provinces/cities, including major cities of Ho Chi Minh City, Hanoi, and Danang, which has directly impacted economic activities and the progress of public projects, forcing many to temporarily stop or preventing foreign consultants from entering Vietnam.
Other issues have also contributed to the delay in the construction progress, including the difficulties in site clearance, resettlement of affected households, slow progress in bidding procedures, or adjustment to financing agreement, Hien continued.
Hien called for greater efforts to accelerate the disbursement of ODA funds in areas with a low risk of infection to compensate for the delayed works at locations under lockdown.
The MoF, for its part, would closely cooperate with other agencies in speeding up the disbursement of public funds, including the ODA and preferential loans, Hien stressed.
Hien called for project owners to enhance efficiency in managing ODA projects and report any difficulties to competent authorities for timely address.
“It is essential for project owners to select qualified and capable consultants in project design to avoid potential modification in the execution,” he said.
In a recent meeting in early October, Deputy Prime Minister Pham Binh Minh suggested the Vietnamese Government is in process of drafting a new decree in replacement of decree No.56 on ODA management, with a view to both simplify the administrative process and ensure efficiency in the use of ODA.
Hanoi is among the cities that were hit hard by the fourth Covid-19 outbreak. The city, however, still posted a positive disbursed amount of ODA funds at VND3.66 trillion ($161 million) in the first nine months of 2021, or 46.7% of the yearly target and up 7.2% year on year. The rate was significantly higher than that of the national average and showcased strong efforts from local authorities to speed up economic recovery, with public investment seen as a major solution to boost growth during the pandemic. |
Other News
- Construction of Hanoi’s Ring-road No.4 set to begin next June
- PM to lead Steering Committee on national key transport projects
- Work kicks off on Vong Xuyen Industrial Cluster
- Hanoi has new high-tech oncology hospital
- Will office rental demand in Vietnam drop as hybrid working gets trendy?
- Transport ministry approves 12 sub-components under North-South expressway projects
- Removing barriers to boost real estate development in Vietnam
- VinFast raises $4 billion for its plant in US
- Hanoi to build regulations on renovating and rebuilding old apartments
- Vietnamese urban architecture: Opening doors for living spaces with past-future harmony
Trending
-
11 Vietnamese scientists named for world research
-
PVN plans to build US$19-billion oil refinery-storage complex
-
“Produce more from less”: Danish agricultural philosophy for Vietnam
-
Over US$34 billion set to pour into Vietnam’s real estate market this year
-
Cultural industry to contribute 5% of Hanoi’s GRDP by 2025
-
Vietnam is stunning in South Korean artist’s MV
-
Hanoi focuses on supporting business recovery: Mayor
-
Construction of Hanoi’s Ring-road No.4 set to begin next June
-
Dolphin shows fascinate audiences in Hanoi