Two causes for delaying test run of Cat Linh-Ha Dong railway

It is expected that the urban railway of Cat Linh - Ha Dong will run technical tests on September 2, 2018, after it missed a scheduled test in October.

The Railway Project Management Unit proposed the Ministry of Transport ask for Prime Minister Nguyen Xuan Phuc’s approval for the rescheduling. The rescheduling means the project will be 11 months delayed from the plan that was adjusted in February 2017.
 
 
the urban railway of Cat Linh - Ha Dong. Photo: Anh Trong
the urban railway of Cat Linh - Ha Dong. Photo: Anh Trong
The railway will operate on a trial basis for three to six months, starting from September 2, 2018, and be put into use in November 2018. This project has been rescheduled three times so far. 

In early 2016, the Transport Ministry asked the China Railway Sixth Group Co. Ltd, the engineering – procurement – construction contractor of the project, to test the railway in September 2016 and launch it by December 31, 2016. As the project lagged behind schedule as of June 2016, the ministry ordered the construction be finished by December 31, 2016.

However, this target was missed, forcing the Transport Ministry to postpone the test run until October 2017 so as to put the railway into operation in the late first quarter or early second quarter of 2018. The project failed to meet this deadline once again.
 
Overview of the urban railway project of Cat Linh - Ha Dong
Overview of the urban railway project of Cat Linh - Ha Dong
The sluggish progress is attributable to various reasons, including slow capital disbursement and the contractor’s limited capacity.

The Cat Linh - Ha Dong urban railway project was started by the Ministry of Transport on October 10,2011, with a total investment of $ 552.86 million, including ODA from the Chinese Government and reciprocal capital of the Vietnamese Government.

In early 2014, the project was proposed by the stakeholders to adjust the total investment from $522.86 million to $868.04 million, an increase of $315.18 million compared to the initial investment.

The government has agreed to borrow an additional $250.62 million from China in order to allocate the majority of the project's total investment, while the rest will be funded by counterpart funds from Vietnam.

 
Reactions:
Share:
Trending
Most Viewed
All citizens can access to affordable housing: PM

All citizens can access to affordable housing: PM

A house is a fundamental right for every citizen and everyone deserves equal, transparent and fair access to housing that fits their paycheck.

Western West Lake area poised to become Hanoi’s next-generation office center

Western West Lake area poised to become Hanoi’s next-generation office center

Driven by expanding metro lines, ring roads and a renewed West Lake master plan, Tay Ho Tay or the western area of the West Lake is emerging as a strategic office hub under Hanoi’s shift toward transit-oriented urban development.

Infrastructure plans fuel surge in Hanoi suburban land auctions

Infrastructure plans fuel surge in Hanoi suburban land auctions

Surging land auctions in Hanoi’s outlying communes, marked by sharply higher winning bids, point to returning capital and renewed confidence, while also stirring debate over speculation risks and whether prices truly reflect long-term demand and market fundamentals.

Tet renovation rush strains Hanoi crews, lifts finishing material costs prices

Tet renovation rush strains Hanoi crews, lifts finishing material costs prices

Hanoi’s home renovation market has entered its busiest stretch of the year, as year-end demand tightens contractor availability and raises the cost of finishing materials.

Vietnam construction materials rebound as prices rise and public investment accelerates

Vietnam construction materials rebound as prices rise and public investment accelerates

Rising steel and cement prices, stronger public investment spending and improving consumption across key material segments point to a broad recovery in Vietnam’s construction materials sector as 2026 begins.

Hanoi sets 40 sq.m housing space goal to lift urban living standards

Hanoi sets 40 sq.m housing space goal to lift urban living standards

Raising average housing space marks a people-centered shift in urban policy as the capital works to improve living standards, expand social housing and ensure that rapid economic growth goes hand in hand with safer and more livable neighborhoods.

Prime Minister urges measures to boost supplies and control house prices

Prime Minister urges measures to boost supplies and control house prices

Vietnam’s government is stepping up efforts to rebalance the real estate market as Prime Minister Pham Minh Chinh urges faster policy action to expand housing supply, address affordability pressures and ensure the sector supports both economic stability and social welfare.

Ho Chi Minh City forms first professional association for apartment management

Ho Chi Minh City forms first professional association for apartment management

Amid rapid urban growth, Ho Chi Minh City has established a professional body for apartment management, becoming the first locality in Vietnam to do so.