Additional US$164 million for Ring Road 4 project in Hanoi

Upon completion and opening to traffic in early 2027, the project is expected to enhance connectivity between Hanoi and other northern provinces and support the socioeconomic development of the entire north region.

Chairman of the Hanoi People's Committee Tran Sy Thanh has signed Decision No. 1814 on revising the city's public investment plan for 2023, including an injection of VND3.84 trillion (US$164 million) for the construction of the Ring Road No. 4 project.

 The design of the Ring Road No.4 project.

Under the plan, an estimated VND3.3 trillion ($140.6 million) would be added to Component 1.1 - Compensation and Resettlement of Affected Households, and VND550 billion ($23.43 million) to Component Project 2.1 - Construction of Urban Roads under Ring Road No. 4 in Hanoi.

The City has allocated VND400 billion ($17 million) for advance disbursement related to technical design, construction drawing, and cost estimation to speed up the investment preparation process.

The Municipal People's Committee has assigned the responsibility of implementing the project within the approved schedule to investors and district and city People's Committees. They are also tasked with ensuring that the project is implemented with maximum efficiency and cost savings while complying with the State and the city's regulations on managing construction investment costs.

In addition, the committee has emphasized the need to accelerate the implementation of key projects and the disbursement of the 2023 Public Investment Plan.

The Ministry of Planning and Investment, the Ministry of Finance, and specialized departments such as Construction and Transport, as well as the Hanoi Department of Finance and related units, are responsible for facilitating, guiding, and expediting the investment, construction, disbursement, and payment procedures of the projects. They must ensure that the investor can implement the project in accordance with State and City regulations on investment and construction management while maintaining progress and quality.

With a length of 112.8 kilometers and an area of 1,341 hectares, Ring Road No. 4 will cut through the towns of Hanoi, Hung Yen, and Bac Ninh. The project, which is expected to cost around VND86 trillion (US$3.64 billion), will be broken down into seven parts, three of which will offer compensation and assistance to households that have been relocated, the other three will use public funds to build urban roads, and the final one will use a public-private partnership to build an expressway.

The project is expected to improve connectivity between Hanoi and other northern provinces upon completion and opening to traffic in early 2027 and support the socio-economic development of the entire northern region, with Hanoi acting as the primary driver of growth.

Reactions:
Share:
Trending
Most Viewed
Related news
Vovinam Dance Contest 2025 kicks off in Hanoi

Vovinam Dance Contest 2025 kicks off in Hanoi

The four-month competition helps everyone understand one of Vietnam's intangible heritages.

Hanoi mayor urges 24-hour processing for key projects

Hanoi mayor urges 24-hour processing for key projects

Key priorities include investment and infrastructure, focusing on public investment, FDI, PPP, industrial parks, high-tech zones, energy, trade, and urban housing.

Hanoi is home to a wealth of 6,500 relics

Hanoi is home to a wealth of 6,500 relics

The number of relics in Hanoi has now reached 6,489 after an inventory.

Hanoi mayor calls for urgent construction of Tu Lien Bridge

Hanoi mayor calls for urgent construction of Tu Lien Bridge

Tu Lien Bridge project, estimated to cost VND22 trillion (US$860 million), is one of Hanoi’s key transportation infrastructure projects, part of the city’s Transport Master Plan to 2030 with a vision to 2050

Hanoi to host Earth Hour 2025 ceremony this weekend

Hanoi to host Earth Hour 2025 ceremony this weekend

The event will feature a range of interactive activities focused on the environment, climate, and energy.

Old apartments transformed into 40-story towers attracting investors

Old apartments transformed into 40-story towers attracting investors

The move is expected to break the long-standing deadlock in the city’s redevelopment efforts for aging residential buildings.

Hanoi sets 95% disbursement target for public investment

Hanoi sets 95% disbursement target for public investment

The move is part of the city’s ongoing effort to push for high economic growth this year.

Global Student Fashion Week to make Hanoi rendezvous for young int'l designers 

Global Student Fashion Week to make Hanoi rendezvous for young int'l designers 

Themed Sustainable Fashion, the event will demonstrate skillful design techniques, convey strong messages about environmental responsibility, recycling culture and application of technology in modern fashion.